S&WB power complex is supposed to be December 18. It was originally scheduled for November 13, but was cancelled. (5/5)
S&WB power complex is supposed to be December 18. It was originally scheduled for November 13, but was cancelled. (5/5)
S&WB power complex equipment since 11/19/25, because the website updates don't mention them. So we don't know if SFC 2 became "available" at the end of November, or if testing of turbine 7 has started. (4/5)
S&WB power complex equipment since 11/19/25, because the website updates don't mention them. So we don't know if SFC 2 became "available" at the end of November, or if testing of turbine 7 has started. (4/5)
internet.deq.louisiana.gov/portal/ONLIN...
internet.deq.louisiana.gov/portal/ONLIN...
www.youtube.com/watch?v=KPey...
www.youtube.com/watch?v=KPey...