Don't take my word for it...here's the word straight from the Legal Notice on the Detroit CBO:
December 16, 2025 at 12:46 AM
Chenita Gary is our next speaker. It is 7:01 p.m. and she said she was appointed by Coleman A. Young Jr.

Says the current agreement she is not in agreement with and has concerns and wants to follow-up with CRIO.

Wants to discuss this in more detail.

All NAC members for Fisher Body listed below:
December 16, 2025 at 12:03 AM
Now for the Q&A and public discussion. Floor is now open for NAC members first....
December 15, 2025 at 11:56 PM
December 15, 2025 at 11:54 PM
Community support and investments, and NAC direction of program dollars explained in the graphic below:

NAC will decide by majority vote.
December 15, 2025 at 11:53 PM
Here we go: the math as it relates to affordable housing -
December 15, 2025 at 11:50 PM
Sustainability, environmental, and accessibility issues discussed, with a focus on ensuring all spaces are open to the public.

ADA accessibility (federal) and the Michigan Buildings Code are featured in this slide.
December 15, 2025 at 11:47 PM
A mayoral executive order was issued for hiring Detroit workers (EO 2024-2):

They admitted they fell by 8 percentage points, so they missed the mark.
December 15, 2025 at 11:45 PM
Mininum $17/hour for sub/contractors on this project is encouraged, and there will be training, mentorship and apprenticeship opportunities available for Detroiters, up to and including through DPSCD.

DPSCD = Detroit Public Schools Community District, the largest public school district in MI
December 15, 2025 at 11:43 PM
EGLE is involved in this project to provide oversight and compliance.

More about EGLE can be found here - www.michigan.gov/egle/
December 15, 2025 at 11:35 PM
Notice: There will be construction weekends - Saturday and Sunday but there should be advance notice given to residents and/or business owners -
December 15, 2025 at 11:32 PM
NAC members toured the area: (no date given)
December 15, 2025 at 11:31 PM
They have also provided a QR code for those interested in learning more, including if you are a contractor:
December 15, 2025 at 11:31 PM
This is the updated project timeline through July 2027 and expectation of project financing soon (January 2026):
December 15, 2025 at 11:29 PM
More renderings and discussion:
December 15, 2025 at 11:28 PM
Before and Now images:
December 15, 2025 at 11:27 PM
More future images/artist renderings:
December 15, 2025 at 11:27 PM
The future (image):
December 15, 2025 at 11:25 PM
Richard of Richard Hosey. Link later in thread.

Trying to keep up with slide presentation and discussion about repair work and progress thus far.
December 15, 2025 at 11:24 PM
And now, Richard is speaking about the actual updates on the construction of the site, seen below (before pictures):
December 15, 2025 at 11:21 PM
ℹ️CRIO Contacts:
December 15, 2025 at 11:20 PM
Allegedly, this is the process if there is disagreement with the findings:
December 15, 2025 at 11:19 PM
December 15, 2025 at 11:18 PM
Monitoring and enforcement by CRIO:
December 15, 2025 at 11:18 PM
CRIO discussing the Tier I projects in the CBO process and how they do their work for development in Detroit:
December 15, 2025 at 11:17 PM